Spring Creek Channel – Flood Control
All Projects
CMTConstruction Materials

Spring Creek Channel – Flood Control

Materials testing and inspection for flood-control channel improvements along Spring Creek in Harris County: density, concrete and placement observation.

Related service: Construction Materials Testing

Spring Creek Channel – Flood Control
Materials testing and inspection for flood-control channel improvements along Spring Creek in Harris County: density, concrete and placement observation.

Related Service

Construction Materials Testing

Concrete, asphalt/pavement, compaction, Proctor, density/moisture, aggregate, special inspection and QA/QC testing.

Scope

Construction materials testing and inspection for flood-control channel improvements along Spring Creek.

Site Challenge

Flood-control channel improvements involve earthwork, concrete and backfill placed in and around an active waterway, where compaction and concrete quality determine whether the channel performs in the next major storm.

Work Performed

Quartet Engineers provided construction materials testing and inspection for the Spring Creek channel improvements: field density testing on fill and backfill, concrete sampling and testing, and observation of placement against the project specifications.

Deliverables

Field and laboratory test reports and inspection records documenting that the earthwork and concrete met specification, issued throughout construction.

More Construction Materials Testing Projects

William Lawson Park – Fitness Improvements

Construction materials testing and inspection for fitness and park improvements at William Lawson Park in Harris County, Texas, from subgrade through concrete.

Rockrose Ranch

Geotechnical and materials testing across the Rockrose Ranch master-planned community: utilities, paving, detention, lift station and amenity-center work.

Hanover Apartments

Materials testing for the Hanover Apartments high-rise in Houston: concrete and compaction testing, asphalt overlay testing and a post-construction review.